Surya can complete a work in 8 days and Mathivennila can complete the same work in 12 days. If both work together, how many days will they take to complete the work?
Question
Surya can complete a work in 8 days and Mathivennila can complete the same work in 12 days. If both work together, how many days will they take to complete the work?
Options
Attempt the question to unlock explanation.
Explanation
Explanation
Step 1: Find daily work rate of Surya and Mathivennila
Step 2: Find combined 1-day work
LCM of 8 and 12 = 24
So, together they do ( \frac{5}{24} ) of the work in 1 day.
Step 3: Find total days to complete 1 work
✅ Answer
4.8 days (Option C)