Quantitative Aptitude · Time & Work
A can do a piece of work in 12 days, B can do the same work in 16 days, and C can do it in 24 days. If they work together, how many days will it take to complete the work?
Question
A can do a piece of work in 12 days, B can do the same work in 16 days, and C can do it in 24 days. If they work together, how many days will it take to complete the work?
Options
Attempt the question to unlock explanation.
Explanation
Step 1: Work done by each per day
Step 2: Total work done by A, B, and C in 1 day
Find LCM of 12, 16, 24 = 48:
Step 3: Total days to complete the work
✅ Answer
Approximately 5 1/3 days (Option B: 5 days)