A and B together can complete a work in 10 days. A alone can do it in 15 days. In how many days can B alone complete the work?

Question

A and B together can complete a work in 10 days. A alone can do it in 15 days. In how many days can B alone complete the work?A and B together can complete a work in 10 days. A alone can do it in 15 days. In how many days can B alone complete the work?

Medium · 2.5 marks