Quantitative Aptitude · Time & Work
A can complete a piece of work in 12 days, and B can complete the same work in 16 days. If they work together, how many days will it take to complete the work?
Question
A can complete a piece of work in 12 days, and B can complete the same work in 16 days. If they work together, how many days will it take to complete the work?
Options
Attempt the question to unlock explanation.
Explanation
Explanation:
- Work done by A in 1 day: 112\frac{1}{12}121 of the work.
- Work done by B in 1 day: 116\frac{1}{16}161 of the work.
- Work done together in 1 day: 112+116=448+348=748\frac{1}{12} + \frac{1}{16} = \frac{4}{48} + \frac{3}{48} = \frac{7}{48}121+161=484+483=487 of the work.
- Total days required: Days=17/48=487≈6.857 days\text{Days} = \frac{1}{7/48} = \frac{48}{7} \approx 6.857 \text{ days}Days=7/481=748≈6.857 days
Rounded to the nearest whole number, it takes approximately 6 days, so the correct option is A. 6 days.