Quantitative Aptitude ยท Time & Work
A can complete a work in 12 days, and B can complete the same work in 16 days. If A and B work together for 4 days and then B leaves, how many more days will A need to finish the r
Question
A can complete a work in 12 days, and B can complete the same work in 16 days. If A and B work together for 4 days and then B leaves, how many more days will A need to finish the remaining work?
Options
Explanation
Problem
A can complete a work in 12 days, and B can complete the same work in 16 days. A and B work together for 4 days, then B leaves. Find how many more days A will need to finish the remaining work.
Solution
Step 1: Work done by A and B per day
A's 1 day work: 112\frac{1}{12}121โ
B's 1 day work: 116\frac{1}{16}161โ
Work done together in 1 day: 112+116=748\frac{1}{12} + \frac{1}{16} = \frac{7}{48}121โ+161โ=487โ
Step 2: Work done by A and B in 4 days
4ร748=2848=7124 \times \frac{7}{48} = \frac{28}{48} = \frac{7}{12}4ร487โ=4828โ=127โ
Remaining work: 1โ712=5121 - \frac{7}{12} = \frac{5}{12}1โ127โ=125โ
Step 3: Days required by A to finish remaining work
Days=512112=5\text{Days} = \frac{\frac{5}{12}}{\frac{1}{12}} = 5Days=121โ125โโ=5
Answer
5ย days\boxed{5 \text{ days}}5ย daysโ