gopi can complete a work in 10 days, and surya can complete the same work in 15 days. If they work together, how many days will it take to finish the work?
Question
A can complete a work in 10 days, and B can complete the same work in 15 days. If they work together, how many days will it take to finish the work?
Options
Attempt the question to unlock explanation.
Explanation
Work done by A in 1 day = 1/10 Work done by B in 1 day = 1/15 Combined work in 1 day = 1/10 + 1/15 = 3/30 + 2/30 = 5/30 = 1/6 Time required = 1 ÷ (1/6) = 6 days