Permutations & Combinations

In how many ways can 4 people be seated in a row?

Time & Work

A can complete a work in 20 days and B can complete it in 30 days. In how many days will they complete the work together?

Time & Work

Surya can complete a work in 15 days and his Future Wife can complete it in 10 days. In how many days will they complete the work together?

Permutations & Combinations

How many 3-letter words can be formed from the letters of ABCDE (no repetition)?

Permutations & Combinations
How many 4-digit numbers can be formed using digits 1, 2, 3, 4, 5 (no repetition)?

Permutations & Combinations

Arrangements of MISSISSIPPI

Permutations & Combinations

In how many different ways can the letters of the word "BANANA" be arranged?

Permutations & Combinations

In how many different ways can the letters of the word "LEVEL" be arranged?

Permutations & Combinations
In how many different ways can the letters of the word "CAT" be arranged?

Time & Work

A can complete a work in 12 days, and B can complete the same work in 16 days. If A and B work together for 4 days and then B leaves, how many more days will A need to finish the remaining work?

Percentages

A shopkeeper increases the price of an article by 20%. If the original price was ₹500, what is the new price?

Time & Work

Praveen can complete a work in 8 days, and his friend Selvaprasath can complete the same work in 12 days. If they work together, in how many days will they finish the work?

Time & Work

A can do a piece of work in 12 days, B can do the same work in 16 days, and C can do it in 24 days. If they work together, how many days will it take to complete the work?

Time & Work

Praveen can complete a work in 20 days. Varun can complete the same work in 30 days. They work together for 6 days, after which Praveen leaves. In how many more days will Varun finish the remaining work?