GS3 Infrastructure
MediumDirective Word: ANALYSE + EXAMINE (hybrid) (Frame → Cause → Effect → Interconnections → Significance)
Answer Hint:
- Thermal 66.9% of 256.1 GW peak (Apr 25) → coal 200 MT stocks stable → dispatchable baseload ≠ replaceable by intermittent RE
- Cause: duck curve + BESS deficit + transmission gap → 30% solar installed ≠ 30% peak utilised → curtailment persists
- Cause: evening/night demand → zero solar → thermal indispensable → RE intermittency = structural dependency on coal
- Effect: 44.61 GW solar added FY26 → daytime RE share ↑ → but peak demand gap widens without storage
- Interconnection: grid stability → curtailment → under-utilisation → RE investment signals weakened → transition slows
- Challenges: BESS deployment lag + transmission infrastructure gap + petroleum outside GST → cascading cost barrier
- Verdict: conventional = indispensable in transition phase → solar + BSD + grid reform = trinity → managed RE dominance, not overnight shift